S
Many
areas of Greene County, particularly Beavercreek and Sugarcreek,
had sewer & water added “after the
fact” (i.e., retrofitted).
This is a much more expensive way to install utility
lines than other jurisdictions in the surrounding areas faced.
S
GCSED
began operations in mid-1960s with construction of the
Beavercreek sanitary sewer system and wastewater treatment
facility.
S
Discussions
on a central water system commenced as early as the mid-1960s
but a majority of Beavercreek Township's population that
attended public meetings/hearings deemed the price too high or
felt that a central system would contribute to more growth.
S
The
1970s saw many developers installing “plat water systems”
that were turned over to the County to own and operate. The
County was operating up to six separate water systems in
Beavercreek at one time.
S
As
Beavercreek continued to grow in the 1970s, more and more
residents were experiencing water problems, such as their wells
going dry. In 1977
the Sanitary Engineer was directed by the Board of Greene County
Commissioners to build a water system in the Beavercreek
Township area for those residents that “needed and wanted
it”.
S
The
resulting water system was a retrofit, designed for just those
that “needed and wanted it”; therefore, it had many dead-end
lines and was fairly inefficient.
S
Both
the community and the water system grew rapidly in the 1980s and
1990s, with Beavercreek attaining the status of a city in the
early 1980s. The
water system grew by 15-20 water extension projects per year,
primarily from petitions by property owners that “needed and
wanted water”. The
water treatment facility was also expanded several times in the
late 1980s and mid-1990s.
S
Expansion
of the Northwest Regional Water System has always been a
balancing act; if it is built too large the current customers
must bear the burden with excessive rate increases; if capacity
lags behind growth, the shortages occur during high demand
periods (summer irrigation periods).
S
The
County worked with a consultant to develop a Comprehensive
Master Plan for the water system that was completed in 2005.
The plan identified and prioritized many projects to
strengthen the system over a 20-year period, as well as what is
needed for a full build-out of the County.
S
The
Executive Summary of that Master Plan is available on the GCSED
web site by clicking here.